Village Center Station (11.1.08)

Pictures of equipment being craned to the roof of the Village Center Station project on Saturday 11/1/08. The crane is a 400 ton hydraulic with a luffer jib furnished by Winslow Crane. We set the upper and lower sections of the Evapco cooling tower, several fans, some prefabricated piping sections and (4) 100 ton McQuay evap condensing rooftop units. Many of the photos were taken from the RTD garage which is across I-25 from the jobsite. The move was accomplished in about 5 hours start to finish, except for crane mobilization and demobilization, which took the better part of a day.

 

 